The storm drain piping on the field is on schedule and proceeding well.
Concrete pouring will happen this week for the scoreboard piers on the hardball and softball fields.
The football scoreboard piers work is being rescheduled due to the need to increase the depth of the piers from 14.25' to almost 20' deep.
Parking Updates:
Palm, Park, Winsor - Parking restrictions remain in place at least through Friday, 10/13, due to the hauling away of the trench spoils and trucking in of drain rock backfill material for the storm drain work.
El Cerrito - Parking restrictions remain in place at least through Friday, 10/13, due to the hauling away of trench spoils and trucking in of drain rock backfill material for the storm drain work.
Witter Field Parking closed to public vehicles through project completion.
Click here for a visual of the completion Schedule as of 9.25.23.
Witter construction completion date target is Monday January 8th, 2024, weather permitting.
Click here to see the full slideshow of the Witter Field Renovation project.
More News
State rank of 3rd in ELA and Math, and 4th in the state for unified school districts on the 2024 CAASPP.
Wildwood Interim Principal Announcement
PMS recognized for preparing students to think critically and use technology responsibly.
Beach, Havens and Wildwood Elementary Schools were selected as California Distinguished Schools for 2023