The PUSD Witter Field Renovation Project Update 7-13-23 provides an update from Pete Palmer, PUSD Director of Facilities/Construction Manager, on anticipated parking restrictions and other impacts for the remainder of July, as well as an update on the drainage calculations.

 

Look Ahead Schedule Highlights - see full schedule here.

7/10/23-7/14/23  Grading at Field and Off-Haul     

7/17/23-7/28/23  Storm Drainage     

7/12/23-7/26/23  Grade at Upper Bleachers     

7/25/23-7/28/23  Electrical at Upper Bleachers     

7/24/23-7/28/23  Channel Drains     

7/31/23-8/11/23  Concrete at Bleachers      

 