This PUSD Witter Field Renovation Project Update Letter 6.22.2023 provides an update from Pete Palmer, PUSD Director of Facilities/Construction Manager, on construction safety requirements for temporary parking restrictions, and Winsor driveway gate closures, as well as addressing drainage calculations.
Look Ahead Schedule Highlights - see full schedule here.
Field Turf - Removal & Off-haul 6/15-6/28
Bleacher - Demo & Off-haul 6/12-6/23
Field Excavation & Off-haul 6/29 -7/6
Storm Drainage 7/7-7/27
PHS Track & Field Drainage - Verde Design
PHS Track & Field Reconstruction Project - Verde Design
More News
New student enrollment for the 2025-26 school year opens January 15th! Residents with children not currently attending Piedmont schools - new kindergarteners or a student switching to Piedmont schools - are invited to start the enrollment process.
State rank of 3rd in ELA and Math, and 4th in the state for unified school districts on the 2024 CAASPP.
Wildwood Interim Principal Announcement
PMS recognized for preparing students to think critically and use technology responsibly.